Pressure of Truth
Exposing the spin on all sides of the news.
U.S.

D.C. Circuit Vacates Energy Department Emergency Order That Kept Michigan's Campbell Coal Plant Running

A three-judge panel ruled unanimously on September 11, 2026 that the Energy Department stretched its Federal Power Act emergency power beyond what the statute allows; the department says the orders prevented blackouts and is weighing an appeal.

How spun is the coverage?Coverage bias 5.0 / 10
4 sides analyzed15 sources cited

A Court Says One Word Doesn't Mean What the Energy Department Says It Means

The J.H. Campbell coal plant in West Olive, Michigan, was supposed to shut down on May 31, 2025[1][2]. Instead, it's still running, kept alive by a federal order that used a single word to override the plant's own retirement date: "emergency"[1][2].

On September 11, 2026, a three-judge panel of the U.S. Court of Appeals for the D.C. Circuit ruled unanimously that the Energy Department stretched that word further than the law allows[1][2][11]. The court vacated the department's original order from May 2025, the one that first forced Campbell to keep operating[1][2][11]. The states of Michigan, Illinois and Minnesota, along with environmental groups, had sued to stop it[2][11].

Here's the tension at the center of the case: the plant did generate real power during a real cold snap this year, running above 650 megawatts every day from January 21 to February 1[13]. And it also cost hundreds of millions of dollars to keep online, money that consumers ultimately help cover[12][14]. Both of those things are true. The fight is over which one the law was built to weigh.

What "Emergency" Is Supposed to Mean, and Why the Difference Matters

Section 202(c) of the Federal Power Act lets the Energy Secretary order a power plant to keep running during an emergency[2]. Historically, that's meant something narrow and sudden: a hurricane knocks out transmission lines, or a generator fails without warning, and a region risks losing power within days[2][5].

Energy Secretary Chris Wright used the provision differently. His argument was that the Midwest grid could run short of power in coming seasons, so keeping a retiring coal plant on standby counted as emergency action, too[2][5]. That's a much bigger claim. It treats a general worry about future supply the same way the law treats a storm bearing down tonight.

The court didn't accept that. It wrote that the text, structure and history of the statute don't support what it called "DOE's sweeping conception" of emergency power[1][2]. In the panel's reading, Section 202(c) is meant for situations that need immediate federal action, not standing insurance against a future shortfall[1][2].

Why does that distinction matter so much? Because if "emergency" can mean "we're worried about six months from now," the Energy Department could use it to keep almost any retiring plant open, almost indefinitely. That's the tool DOE wants to preserve, and it's the tool the challengers say was never meant to exist.

Six Emergencies, One Plant

The record made the challengers' case for them. DOE didn't invoke emergency power once for Campbell — it did so six times, reissuing the order every 90 days, most recently on August 14, 2026[2][12]. Michigan Attorney General Dana Nessel, who led the lawsuit, argued that an emergency renewed six times in a row isn't really an emergency at all[11][2]. It's a policy, she said, imposed without the normal process of hearings and evidence that energy regulation usually requires[11][3].

There's also a cost question sitting underneath the legal one. Consumers Energy, the utility that owns and runs Campbell, says it spent $164 million keeping the plant available through the first order and part of the second, and took an $80 million loss doing it[12]. Total figures for the whole stretch run higher — about $259 million by one count, $295 million by the company's own financial filings through June 30, 2026, with the gap likely reflecting different end dates and counting methods rather than a real disagreement over the number[2][12].

Consumers isn't fighting the order; it's complying with a federal directive while trying not to eat the cost. It has sought to recover its spending through a mechanism approved by the Federal Regulatory Energy Commission (FERC), which spreads the bill across customers in MISO's central and northern zones — the regional grid that includes Michigan and neighboring states[12][14]. The challengers say that violates a principle called "cost causation," the idea that the people who benefit from a cost should be the ones paying it, not customers elsewhere in the region who had no say in the decision[12][14]. That fight is still going on at FERC, separate from the court ruling[12][14].

The Case for Keeping Campbell Running

DOE's strongest argument isn't really about Campbell specifically — it's about what happens when a power plant goes away and doesn't come back. Once a coal unit retires, workers leave, fuel contracts end, and restarting the plant later can take months or years[8][2]. A retirement, in other words, is close to permanent. Whoever controls the power to delay one effectively controls part of the region's fuel mix.

DOE points to hard numbers to back its case. During Winter Storm Fern in January, coal generation across the affected region rose 25% compared with the same period a year earlier, and Campbell itself ran above 650 megawatts every day for eleven straight days[13]. The department says its orders "prevented blackouts and likely saved hundreds of lives"[13][2]. Coal, in this argument, offers something wind and solar can't guarantee on demand: fuel stored on site, ready to burn the moment the grid calls for it.

The coal industry's own trade group, America's Power, took the argument further, dismissing the ruling in a post titled "The Baseload: Federal Court in DC Relies on Pixie Dust and Fairy Sprinkles," and argued that judges applying dictionary definitions of "emergency" aren't equipped to judge grid engineering[8]. Behind that argument sits a plainer interest: every avoided retirement extends the life of coal mines, rail contracts and plant jobs tied to plants like Campbell[8].

This is also playing out against a backdrop of genuinely rising demand. Electricity forecasts across MISO and other regional grids have jumped after years of flat growth, driven by data centers and new manufacturing[2][5]. That rising demand is real, and it's part of what makes DOE's emergency argument plausible to grid planners even without a storm on the radar[2][5].

What the Ruling Actually Changes, and What It Doesn't

The panel vacated only the first order, the one from May 2025[11]. DOE had already reissued the Campbell order five more times since then, and the ruling doesn't automatically erase those later orders[2][12]. Hours after the decision came down, Wright issued a fresh 90-day emergency order for a coal plant in Washington state, a sign the department isn't backing off the broader strategy[2].

Campbell is one of roughly six coal-fired plants DOE has ordered to keep running under this emergency authority since January 2025, with others located in Indiana, Pennsylvania, Colorado and Washington state[2][5]. A narrower reading of Section 202(c) weakens the legal ground under all of those orders, even though this ruling technically applies only to Campbell's first one[2][5]. DOE hasn't conceded any error and can still ask the full D.C. Circuit to rehear the case, or take it to the Supreme Court[2][13].

Coverage of the ruling split along familiar lines. Left-leaning and climate outlets led with cost and the word "illegal" — Inside Climate News called the plant "costly" in its headline, and Common Dreams quoted advocates calling it "old, expensive, and dirty," while largely leaving out DOE's Winter Storm Fern data[3][4]. Right-leaning coverage was thinner and leaned on the reliability argument, with the Washington Examiner framing the ruling as narrowing federal power to only "immediate" action[7]. Al Jazeera and Bloomberg treated it mainly as a check on presidential power, largely skipping the grid-engineering dispute that drives the U.S. debate[2][5].

What happens to the other five orders, and to the hundreds of millions already spent, is still an open question. The FERC cost fight continues on its own track, separate from anything the D.C. Circuit decided[12][14]. And DOE's next move — appeal, rehearing, or simply issuing more orders like the one it signed hours after losing this one — will decide how much this ruling actually restrains[2][13].

Like this article?

Share this article

The Bias Ledger average rating 5

The same story, as framed by outlets across the spectrum, ordered least to most biased. The bias score (1 = straight, 10 = heavily spun) is an AI assessment of that framing — click an outlet to see its track record. The tell is the word choice or omission that reveals the angle.

OutletVantageBiasHow they frame itThe tell
Associated PressU.S. center2'Federal court rejects Trump order keeping Michigan coal plant open' — straight account of the holding, with Wright's reliability rationale stated and the ~$259 million cost attributed to critics[6].Frames the case around 'Trump' rather than DOE, which personalizes an agency-authority ruling; otherwise attributes the cost figure rather than asserting it.
Utility DiveU.S. trade press, utility-sector readership3'Court rejects DOE "emergency" order delaying coal plant retirement as overstep' — leads with the statutory holding and the panel's quoted language[2].Puts 'emergency' in scare quotes in the headline, adopting the challengers' characterization; compensates with the most complete record of DOE's rebuttal, appeal options and the FERC cost track.
Al JazeeraQatari state-funded3'US court rejects Trump's emergency order keeping Michigan coal plant open' — positions the story as a judicial check on presidential power[5].Executive-power frame crowds out the grid-engineering dispute that actually divides U.S. experts.
The Epoch TimesU.S. right, Falun Gong-affiliated4'DC Appeals Court Voids Federal Order Keeping Michigan Coal Plant Open' — procedural headline, with DOE's blackout-prevention claim given prominent placement[15].Neutral verb choice, but the outcome is reported largely through DOE's response rather than the opinion's reasoning.
Washington ExaminerU.S. right5'Federal court knocks down order saving Michigan coal plant' — 'saving' the plant frames the vacated order as a rescue rather than a mandate[7].Emphasizes that 202(c) is limited to 'immediate federal action,' a framing that keeps the loss narrow and technical; the repeat-order pattern and cost totals get little space.
Inside Climate NewsU.S. left-leaning, nonprofit climate newsroom (foundation-funded)6'Court Rules Against Trump Order to Keep Costly Michigan Coal Plant Running' — the word 'costly' carries a verdict in the headline[3].Cost to ratepayers leads; DOE's Winter Storm Fern operating data appears late or not at all.
Common DreamsU.S. progressive advocacy news8'Federal Appellate Court Kills Trump Bid to Keep "Old, Expensive, and Dirty" Coal Plant Open' — built almost entirely from advocacy-group statements[4].'Kills' and the quoted epithet do the argument's work; no reliability evidence from DOE is engaged.
America's Power (Opinion)U.S. coal industry trade association9'Federal Court in DC Relies on Pixie Dust and Fairy Sprinkles in Decision Revoking DOE Emergency Order Authority'[8].Ridicule substitutes for engagement with the statutory text; useful as the industry's undiluted position, not as reporting.

References

  1. DC Circuit Rejects Energy Department's Claim of "Emergency" Authority to Order Coal Plant to Remain Open — Reason (Volokh Conspiracy) · U.S. libertarian; legal-academic blog hosted by a libertarian magazine
  2. Court rejects DOE 'emergency' order delaying coal plant retirement as overstep — Utility Dive · U.S. trade publication for the utility industry, ad-supported
  3. Court Rules Against Trump Order to Keep Costly Michigan Coal Plant Running — Inside Climate News · U.S. left-leaning nonprofit climate newsroom, foundation-funded
  4. Federal Appellate Court Kills Trump Bid to Keep 'Old, Expensive, and Dirty' Coal Plant Open — Common Dreams · U.S. progressive advocacy news nonprofit
  5. US court rejects Trump's emergency order keeping Michigan coal plant open — Al Jazeera · Qatari state-funded international broadcaster
  6. Federal court rejects Trump order keeping Michigan coal plant open — Associated Press · U.S. nonprofit wire cooperative, centrist
  7. Federal court knocks down order saving Michigan coal plant — Washington Examiner · U.S. conservative
  8. The Baseload: Federal Court in DC Relies on Pixie Dust and Fairy Sprinkles in Decision Revoking DOE Emergency Order Authority — America's Power · U.S. coal industry trade association (advocacy)
  9. Trump Administration Loses First Court Case Challenging DOE Orders for Coal Plants — Earthjustice · U.S. environmental litigation nonprofit; a party to the case
  10. Court Overturns DOE Order Forcing Michigan Coal Plant to Stay Open — Natural Resources Defense Council · U.S. environmental advocacy nonprofit
  11. Federal Appeals Court Vacates First DOE Order Forcing Operation of J.H. Campbell Coal Plant — Michigan Department of Attorney General · U.S. state government; office held by a Democrat and a party to the case
  12. Nessel vows another challenge as DOE issues 6th order keeping Campbell plant open — Michigan Advance · U.S. left-leaning nonprofit state newsroom (States Newsroom network)
  13. Energy Secretary Prevents Closure of Coal Plant That Provided Essential Power During Winter Storm — U.S. Department of Energy · U.S. federal agency; a party to the case
  14. Groups challenge MISO cost allocation plan for coal power plant — Utility Dive · U.S. utility-industry trade publication
  15. DC Appeals Court Voids Federal Order Keeping Michigan Coal Plant Open — The Epoch Times · U.S. right-leaning outlet affiliated with the Falun Gong movement